Week 22 – Second Story Framing

November 16, 2025 by sivarajan home

Second story framing is almost complete and ready for trusses. Trusses should be ready in the next week or 10 days. Rain during this week will slow things down a bit, but the project is moving at a steady pace with no major issues. Dumpster was ordered and lot has been cleaned of excess debris.