• Skip to main content

Sivarajan Home

Sivarajan Custom Home

  • home
  • blog
  • 360
  • renderings
  • builders
  • Finishes

Week 38 – building the stem wall for the garage.

April 6, 2026 by sivarajan home

Building the stem wall for the garage. Backfill early next week, and foots poured by end of week or following week.

20260401_121037
20260402_100735
20260402_100730
previous arrow
next arrow

Filed Under: sivarajan home build

Week 34-35: Lot and lots of digging (hard and soft) and some concrete pour.

March 7, 2026 by sivarajan home

Lots and lots of digging -both hard and soft- and there was a concrete pour for both the two patios and the garage footing. Lot is looking amazing as to its size in the back for adding all sorts of kids stuff and for the pool area. Plumbers are almost complete with rough-in and electrical is over fifty-percent complete. Now that the footing is poured, the block for the garage stem wall should start in Monday, with the additional footings be dug and ready for rebar, inspection and pour shortly after. Once the garage footing is complete -next 10 days- then the garage can be built which should take around a week. In essence, the house should be completely closed in by the end of March or early April. That is the goal.

20260226_090211
20260305_074824
20260226_091125
20260225_121901
20260227_110052
20260303_102802
IMG_20260307_094802
20260226_091314
IMG_20260307_094812
previous arrow
next arrow

Filed Under: sivarajan home build

Week 32-33: Plumbing; Electrical and Excavation

February 17, 2026 by sivarajan home

LOTS of excavation work done over the last two weeks as well as rough plumbing and rough electrical; both of which are almost complete. This week will focus on some additional hard dig for both the garage wall, for the lift station and for the drainage ditch needed on the side of the house near the rocks to secure proper water flow there when it rains. Block wall for the garage has been scheduled for next week which will allow for building the garage to happen shortly after. With of course, adjustments for the weather.

20260213_122650
20260213_121512
20260216_094003
20260216_095724
previous arrow
next arrow

Filed Under: sivarajan home build

Week 31 – Sealing Walls and Excavating

February 1, 2026 by sivarajan home

This week was about sealing walls (water proofing) and excavation. A LOT of dirt was moved from the front of the house to the garage side and back of the house. Footings will be dug early this next week for the retaining walls needed for the garage and footings should ready to pour by end of week.

20260129_100220
20260129_100424
20260129_100441
20260129_100506
previous arrow
next arrow

Filed Under: sivarajan home build

Week 29-30: Framing | Plumbing | Electrical | Prepping for Garage

January 17, 2026 by sivarajan home

Framing for house is pretty much completed; electrical has started; plumbing has started. The lot has been cleared to prepare for excavation for garage which needs to happen to accommodate the walls to contain the garage area and for the garage footings. This week electrical and plumbing will continue and walls will be sealed -waterproofed- so dirt for garage pad can be adjusted accordingly. Excavation for garage is being scheduled for this week or next.

20260116_072910
20260116_073826
20260116_073053
20260116_073035
20260116_072809
previous arrow
next arrow

Filed Under: sivarajan home build

Week 28 – Block Walls Completed

December 30, 2025 by sivarajan home

Block walls for the house have been completed and passsed inspection and are ready for grouting. Grouting will allow for the final framing to be completed within the next few weeks. Schedule will partially depend on who takes how long off for New Years. Have a Happy New Year : )

20251226_114910
20251226_114832
20251226_114857
20251226_114835
previous arrow
next arrow

Filed Under: sivarajan home build

Week 26-27 – Still More Framing

December 21, 2025 by sivarajan home

Framing and block work continues and almost complete. Electricians have started on the lower floor. Next up windows, more block work for driveway and backfill.

20251218_095548
20251218_095914
20251218_100502
20251218_100523
20251218_100628
previous arrow
next arrow
20251218_100920
20251218_100735
20251218_100819
previous arrow
next arrow

Filed Under: sivarajan home build

Week 25 – Framing, Framing, Framing

December 6, 2025 by sivarajan home

Framing, framing, and more framing. Plus some clean-up.

20251205_080343
20251205_080959
20251205_080514
20251205_080627 (1)
20251205_080800
20251205_080723
previous arrow
next arrow

Filed Under: sivarajan home build

  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Go to Next Page »

Copyright 2025 - Sivarajan Home