• Skip to main content

Sivarajan Home

Sivarajan Custom Home

  • home
  • blog
  • 360
  • renderings
  • builders
  • Finishes

Week 49-51: Stucco; Electrical and Bedroom Deck

June 29, 2026 by sivarajan home

Stucco; Electrical and Bedroom Deck are all in full swing.

image-1a
image-1b
image-1c
previous arrow
next arrow

Filed Under: sivarajan home build

Week 45-48: HVAC; Garage and Roof

June 21, 2026 by sivarajan home

HVAC rough is complete and ready for inspection. Garage has been built and the roof is complete as well. Looking forward to moving ahead with electrical and plumbing.

20260529_101632
20260604_084556
20260616_085732
previous arrow
next arrow

Filed Under: sivarajan home build

Week 43-44: Garage Slab; HVAC; Stucco and more

May 24, 2026 by sivarajan home

Lots of different work on the house this last two weeks including HVAC close in, garage slab being poured and stucco started. Garage framing also started this weekend.

20260526_083837
20260529_101632
20260526_101910
20260527_084016
20260529_105559
20260527_085838
previous arrow
next arrow

Filed Under: sivarajan home build

Week 41-42: Garage Stem Wall, Roofing and HVAC

May 10, 2026 by sivarajan home

Focus for weeks 41-42 were completing the garage footing and stem wall, getting HVAC ready for roofing and first coat of roofing complete to prepare for stucco. Doors and windows were completely prepped for stucco which is schedule to start this next week.

20260429_100107
20260504_094320
20260508_124249
20260506_085038
20260427_091813
20260505_104523
20260505_104510
previous arrow
next arrow

Filed Under: sivarajan home build

Week 39-40 Adding garage stem wall and digging footing for backyard area

April 24, 2026 by sivarajan home

Primary focus was getting the outside stem wall for the garage completed to the remainng footing could be poured and work on the garage could start. Also, the footing for the backyard area was dug and materials have been dropped to start building the backyard parameter wall out next week. Work was also done on the interior and on the roof to prep for the HVAC which will begin next week which will allow the roofers to roof and the stucco to be added.

20260415_085540
20260402_100730 (1)
20260414_112527
20260414_111454
20260415_085702
previous arrow
next arrow

Filed Under: sivarajan home build

Week 38 – building the stem wall for the garage.

April 6, 2026 by sivarajan home

Building the stem wall for the garage. Backfill early next week, and foots poured by end of week or following week.

20260401_121037
20260402_100735
20260402_100730
previous arrow
next arrow

Filed Under: sivarajan home build

Week 34-35-36: Lot and lots of digging (hard and soft) and some concrete pour.

March 7, 2026 by sivarajan home

Lots and lots of digging -both hard and soft- and there was a concrete pour for both the two patios and the garage footing. Lot is looking amazing as to its size in the back for adding all sorts of kids stuff and for the pool area. Plumbers are almost complete with rough-in and electrical is over fifty-percent complete. Now that the footing is poured, the block for the garage stem wall should start in Monday, with the additional footings be dug and ready for rebar, inspection and pour shortly after. Once the garage footing is complete -next 10 days- then the garage can be built which should take around a week. In essence, the house should be completely closed in by the end of March or early April. That is the goal.

20260226_090211
20260305_074824
20260226_091125
20260225_121901
20260227_110052
20260303_102802
IMG_20260307_094802
20260226_091314
IMG_20260307_094812
previous arrow
next arrow

Filed Under: sivarajan home build

Week 32-33: Plumbing; Electrical and Excavation

February 17, 2026 by sivarajan home

LOTS of excavation work done over the last two weeks as well as rough plumbing and rough electrical; both of which are almost complete. This week will focus on some additional hard dig for both the garage wall, for the lift station and for the drainage ditch needed on the side of the house near the rocks to secure proper water flow there when it rains. Block wall for the garage has been scheduled for next week which will allow for building the garage to happen shortly after. With of course, adjustments for the weather.

20260213_122650
20260213_121512
20260216_094003
20260216_095724
previous arrow
next arrow

Filed Under: sivarajan home build

  • Page 1
  • Page 2
  • Page 3
  • Interim pages omitted …
  • Page 5
  • Go to Next Page »

Copyright 2025 - Sivarajan Home