LOTS of excavation work done over the last two weeks as well as rough plumbing and rough electrical; both of which are almost complete. This week will focus on some additional hard dig for both the garage wall, for the lift station and for the drainage ditch needed on the side of the house near the rocks to secure proper water flow there when it rains. Block wall for the garage has been scheduled for next week which will allow for building the garage to happen shortly after. With of course, adjustments for the weather.