Lots and lots of digging -both hard and soft- and there was a concrete pour for both the two patios and the garage footing. Lot is looking amazing as to its size in the back for adding all sorts of kids stuff and for the pool area. Plumbers are almost complete with rough-in and electrical is over fifty-percent complete. Now that the footing is poured, the block for the garage stem wall should start in Monday, with the additional footings be dug and ready for rebar, inspection and pour shortly after. Once the garage footing is complete -next 10 days- then the garage can be built which should take around a week. In essence, the house should be completely closed in by the end of March or early April. That is the goal.