Primary focus was getting the outside stem wall for the garage completed to the remainng footing could be poured and work on the garage could start. Also, the footing for the backyard area was dug and materials have been dropped to start building the backyard parameter wall out next week. Work was also done on the interior and on the roof to prep for the HVAC which will begin next week which will allow the roofers to roof and the stucco to be added.