Floor trusses were delivered at the end of week 20 so week 21 started with adding the second-story floor trusses, second story flooring and second story walls. Block work continued thoughout week. Additional lumber was also dropped. Should be ready for roof trusses next week as long as the trusses are ready.
Week 20 – Block Walls and Trusses
Trusses have been delivered and block wall almost complete and ready for inspection. Trusses will start being placed this next week.
Week 19 – Completing Block Walls
Block walls are being completed. Block wall inspection for grout next week. Trusses have been certified by engineer and are now being built. Should be onsite in the next week or two.
Week 18: Framing & Block Wall cont.
Framing and block wall are continuing. Truss specs have gone to the engineer for certification.
Week 17 – Framing & Block Wall
Framing continues and the front CMU is being built and first section should be ready for inspection on Monday.
Week 16 – Framing Continues
Framing has come a long way in the last week. Trusses are expected this next week.
Week 15 – Framing Started
Framing of the house has started. The goal is to have the majority of the structure framed by the end of the week.
Week 14 – Pad Poured and Ready for Framing
Foundation pad has been poured and is ready for framing. Framing will start as soon as the lumber is dropped on Wednesday or Thursday of the week of 09-22-2025 (or this week).