All rough plumbing has been covered with quarter minus and wrapped and has passed inspection. After passing inspection, pipes have been covered and now the pad is being cleared of excess dirt and ready for slab pour which included compacting the dirt and covering with AB. Pad should be ready for inspection next week with the slab pour to follow.
sivarajan home build
Week 8 – Block for Stem Walls
Block for stems walls have been added with inspection shortly.
Week 7 – Block Stem Walls
Footing stem walls being built. Once steel has been place they can be inspected and then grouted prior to slab pour.
Week 6 – Pouring the Footings
After 2-3 weeks of very hard digging in hardpan, the footings for the house foundation and walls were poured this week.
Week 5 – Footings
After a very tough two weeks of digging in hardpan, the footings are just about completed and ready for inspection and pour. Inspections are scheduled for early next week, with a pour to follow immediately after. Block walls should be able to start towards the end of the week.
Week 4: Digging the Footings (still)
Ended week two of digging the footings with a slowdown due to over 50 hours of digging in hardpan. Footings should be dug and rebar laid early next week making them ready for inspection and pour.
Week 3: Footings Being Dug
Footings were started early this week and should be finished by early next week. Hit hard pan in some areas and needed to bring in more robust equipment to complete the task. The goal is to have the footings inspected by mid next week with the goal of pouring them by the end of the week.
Week 2: Survey Completed
The survey to lay out the home has been completed. On Monday, a crew will come in and start to dig all the footings for the home and retaining walls.