• Skip to main content

Sivarajan Home

Sivarajan Custom Home

  • home
  • blog
  • 360
  • renderings
  • builders
  • Finishes

sivarajan home

Week 11-13 – Covering / Wrapping Pipes and Clearing Pad for Pour

September 13, 2025 by sivarajan home

All rough plumbing has been covered with quarter minus and wrapped and has passed inspection. After passing inspection, pipes have been covered and now the pad is being cleared of excess dirt and ready for slab pour which included compacting the dirt and covering with AB. Pad should be ready for inspection next week with the slab pour to follow.

20250912_080114
20250912_080041
20250912_081152
20250912_080830
previous arrow
next arrow

Filed Under: sivarajan home build

Week 9&10 – Filling Stem Walls

August 17, 2025 by sivarajan home

Inspection for stem walls passed and walls have been grouted. Rough plumbing has passed inspection. Shading over plumbing inspection is next. Then lot will be leveled and ab will be added and compacted making it ready for foundation and footing pour.

20250815_082056
20250815_082037
20250814_073158
20250815_082218
previous arrow
next arrow

Filed Under: Uncategorized

Week 8 – Block for Stem Walls

August 5, 2025 by sivarajan home

Block for stems walls have been added with inspection shortly.

20250805_074836
-7790364327067354182
-4941021636519334926 (1)
20250805_074708
20250805_074647
previous arrow
next arrow

Filed Under: sivarajan home build

Week 7 – Block Stem Walls

July 28, 2025 by sivarajan home

Footing stem walls being built. Once steel has been place they can be inspected and then grouted prior to slab pour.

7926106559688683797
1620604830410295228
-1016003746522296271
previous arrow
next arrow

Filed Under: sivarajan home build

Week 6 – Pouring the Footings

July 20, 2025 by sivarajan home

After 2-3 weeks of very hard digging in hardpan, the footings for the house foundation and walls were poured this week.

2601638494907571101
-2810821855945165845
6825150844337132256
7105249311785559384
previous arrow
next arrow

Filed Under: sivarajan home build

Week 5 – Footings

July 12, 2025 by sivarajan home

After a very tough two weeks of digging in hardpan, the footings are just about completed and ready for inspection and pour. Inspections are scheduled for early next week, with a pour to follow immediately after. Block walls should be able to start towards the end of the week.

20250709_083800
20250709_083832
20250709_084105
20250709_084037
20250709_084044
previous arrow
next arrow

Filed Under: sivarajan home build

Week 4: Digging the Footings (still)

July 5, 2025 by sivarajan home

Ended week two of digging the footings with a slowdown due to over 50 hours of digging in hardpan. Footings should be dug and rebar laid early next week making them ready for inspection and pour.

20250703_084328
20250703_084631
20250703_084357
20250703_084623
previous arrow
next arrow

Filed Under: sivarajan home build

Week 3: Footings Being Dug

June 27, 2025 by sivarajan home

Footings were started early this week and should be finished by early next week. Hit hard pan in some areas and needed to bring in more robust equipment to complete the task. The goal is to have the footings inspected by mid next week with the goal of pouring them by the end of the week.

4107733795660168858
-4386663320996445512
-3866925827886085162
previous arrow
next arrow

Filed Under: sivarajan home build

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Page 5
  • Go to Next Page »

Copyright 2025 - Sivarajan Home