After a very tough two weeks of digging in hardpan, the footings are just about completed and ready for inspection and pour. Inspections are scheduled for early next week, with a pour to follow immediately after. Block walls should be able to start towards the end of the week.
Week 4: Digging the Footings (still)
Ended week two of digging the footings with a slowdown due to over 50 hours of digging in hardpan. Footings should be dug and rebar laid early next week making them ready for inspection and pour.
Week 3: Footings Being Dug
Footings were started early this week and should be finished by early next week. Hit hard pan in some areas and needed to bring in more robust equipment to complete the task. The goal is to have the footings inspected by mid next week with the goal of pouring them by the end of the week.
Week 2: Survey Completed
The survey to lay out the home has been completed. On Monday, a crew will come in and start to dig all the footings for the home and retaining walls.
Starting to build the Sivarajan Home
Starting the build.